EN
Technical Support

Technical Support

Site Preparation Before Machine Installation

To ensure smooth installation, commissioning and operation of the machine, please complete the following site preparations before the equipment arrives.

  1. Electrical Power Cable

Prepare a four-core 4 × 16 mm² power cable. The required cable length should be determined according to the distance between the main electrical distribution box and the machine installation position.

  1. Power Supply

The standard power supply requirement is:

380 V / 50 Hz / Three Phase

The available electrical capacity should be no less than 35 kW. The final power requirement depends on the selected machine model, installed components and maximum rated power.

  1. Compressed Air Supply

Prepare an air compressor capable of providing stable compressed air at approximately 8 bar.

When an existing factory air compressor is available, it may be connected to the machine through a suitable compressed-air pipeline.

  1. Compressed-Air Hose

Prepare an air hose with a diameter of approximately 8 mm. The required hose length depends on the distance between the factory air compressor and the machine.

  1. Water Supply

Prepare a water pump with an approximate power rating of 1.5 kW and a 50 mm connection diameter.

The water supply system should provide sufficient and stable water flow for normal machine operation.

  1. Installation Foundation

The machine should be installed on a solid, level and load-bearing concrete floor.

The installation area must provide sufficient space for machine operation, maintenance, material loading and unloading.

  1. Wastewater Settling System

Prepare a three-compartment wastewater settling tank with a total capacity of approximately 10–12 m³.

The settling system is used to separate sludge, abrasive residue and wastewater generated during machine operation, helping improve wastewater circulation and simplify cleaning.

Important Notice

The above requirements are general installation guidelines. Electrical capacity, cable size, air supply, water supply, foundation conditions and wastewater system requirements may vary depending on the machine model and configuration.

Please confirm the final installation requirements with Yongtao Machinery before preparing the factory site.



Contact Us